How to change a commercial maintenance contractor
Start with the date responsibility changes hands. List the plant, the work already due and the person authorised to approve repairs. Both suppliers and the building manager can then see who owns each task during the changeover.
Before giving notice
Check the signed agreement for the renewal date, notice period, notice method and any arrangements for returning records. Record the last day of the current service and the first day of the incoming service separately. Ask the person who manages the contract to confirm them.
Walk the building with the asset list. Mark missing items, plant that has been removed and areas that need landlord or tenant access. A partial list is a workable starting point if the gaps are visible to everyone quoting.
What should the outgoing contractor hand over?
- Asset register. Ask for the equipment reference, location, system served and any access restrictions.
- Visit and inspection records. Collect the latest reports and the basis for each next due date. Identify work due during the changeover.
- Open actions. Give every unresolved fault an owner, report reference, current status and next decision. Record whether a quotation or repair has been authorised.
- Operating information. Locate manuals, drawings, warranty conditions and the people authorised to arrange access or isolation. Agree a secure method for passing access information.
On the day responsibility changes
Arrange a short handover with the building manager and incoming lead. Confirm the first planned visit, the route for a daytime or out-of-hours fault, and who can approve chargeable work. Where responsibilities overlap, give each open task one named owner and a review date.
Worked example. An office air handling unit has a booked service after the changeover and a reported fan fault that is still open. Record the last report against the unit, agree who will diagnose the fault and keep the planned visit on the schedule until its scope is confirmed. This prevents a diary change from closing a live fault.
At the first review
Compare the first visit report with the handover list. Check that outstanding defects still have an owner, next visits appear on the planner and the right people receive reports. Give the managing agent or building owner one dated copy of the updated action list.
Use the plant records guide to organise the evidence and the proposal comparison checklist to check the incoming scope.
Discuss your changeover